The Spire of Dublin

The 1000 tonne lifting crane is now in position in O’Connell Street and the delivery of the first Spire elements is expected in the early part of December. The final shot peening finishing of the stainless steel Spire elements by MIC at Radley Engineering has begun in Dungarven and final inspections begin on 2nd December. The final factory test assembly of the cast and machined spiral base elements will be inspected on 2nd December at Westley Engineering, Cradley Heath, West Midlands, near Birmingham.